A.0.80
B.0.16
C.1.60
D.0.10
您可能感興趣的試卷
你可能感興趣的試題
A.Parallel and Serial
B.Serial and Asynchronous
C.Parallel and Synchronous
D.Synchronous and Asynchronous
A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure.
Which solution addresses the customer requirements?()
A.Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs
B.Move the existing physical network and storage adapters to the new system and virtualize the I/O using a single VIO Server.
C.Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC connectors and dual HBAs.
D.Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC connectors and the other with dual HBAs.
A customer would like to have the ability to permanently activate processor and memory resources as their workload increases.
Which of the following supports the customer requirement?()
A.Reserve Capacity on Demand
B.Utility Capacity on Demand
C.Capacity Upgrade on Demand
D.Uncapped Capacity on Demand
When a customer attempts to manage virtual machines, virtual images and system pools with the VMControl Express Edition, all operations fail except for managing virtual machines.
What is recommended to resolve this situation?()
A.Upgrade to VMControl Standard Edition
B.Upgrade to VMControl Enterprise Edition
C.Upgrade to latest version of VMControl Express Edition
D.Download the latest fixes for VMControl Express Edition
A.Manage multiple operating systems on a server
B.Manage energy consumption and network traffic to increase efficiency
C.Manage LPARs, operating systems and servers to reduce administration
D.Manage workloads across multiple servers to optimize resource utilization
最新試題
A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()
Which of the following items in a single enclosure Power 770 improves Reliability, Availability, and Serviceability?()
A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools.What is the minimum PowerVM Edition which provides this feature?()
A customer is evaluating PowerVM and VMware to run a data warehouse application. Which feature of PowerVM should be highlighted as a differentiator?()
Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations.Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()
A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer.Which of the following must also be ordered?()
A customer requires their application to have high availability within a data center, and also the ability to recover at a data center located 600km away in the event of an outage.Which system software solution component supports the customer requirement?()
Which of the following is a compelling reason to deploy IBM Systems Director Active Energy Manager (AEM) in a data center with high energy utilization?()
A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()
A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in thefollowing configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host1 hosted IBM i partition; 2 hosted Linux partitions.Which configuration will provide boot disk capability to all partitions?()