A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention.
Which of the following meets the customer requirement?()
A.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be capped.
B.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be uncapped.
C.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partitions to use no more than one core. Configure the HMC scheduler to dynamically assign processors among the pools over a day.
D.Create a shared processor pool for each production partition, with the maximum processor limit set to the licensing limit for the application in the pool. Assign the development and testing partitions to a processor pool with a maximum of 1 core. Configure each partition to use uncapped processing.
您可能感興趣的試卷
你可能感興趣的試題
A.8 desired processing units and 8 desired virtual processors
B.2 desired processing units and 8 desired virtual processors
C.8 desired processing units and 32 desired virtual processors
D.2 desired processing units and 32 desired virtual processors
A.PCIe adapters
B.PCI-X adapters
C.PCI-X andPCIe adapters
D.PCI, PCI-X andPCIe adapters
A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750.
Which action allows the most efficient use of existing equipment?()
A.Populate the Power 750 first then add a GX+ adapter to support PCI-X andPCIe I/O drawer loops.
B.Populate the Power 750 first then add 2 GX+ adapters to support PCI-X andPCIe I/O drawer loops.
C.Populate the Power 750 first then add a GX++ adapter to support PCI-X andPCIe I/O drawer loops.
D.Populate the Power 750 first then add GX+ and GX++ adapters to support PCI-X andPCIe I/O drawer loops.
A.PowerVM offers partition mobility.
B.PowerVM can virtualize network and SAN resources.
C.PowerVM supports multiple operating systems running concurrently.
D.PowerVM allows an LPAR to use activated cores and memory without limitation.
A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in thefollowing configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host1 hosted IBM i partition; 2 hosted Linux partitions.
Which configuration will provide boot disk capability to all partitions?()
A.Use dual-split backplane in both enclosures for the three AIX partitions and the IBMi partition.
B.Put each partition on a dedicated controller using the triple-split backplane option in both enclosures.
C.Use the triple-split backplane option in one enclosure for the AIX partitions, and the default dual-split backplane for the IBMi partition in the second enclosure.
D.Use the triple-split backplane option in one enclosure for the AIX partitions, and the non-split backplane mode in the second enclosure for the IBMi hosting partition.
最新試題
Which operating system can directly host managed storage for IBM i, AIX, Linux, VMware and Windows on a Power Systems server?()
Which of the following has an integrated database?()
While using virtualization to share SAN adapters on a server, how does Node Port ID Virtualization (NPIV) differ from Virtual SCSI (vSCSI) related to the use of multipathing software?()
A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs.How can they manage the new machines for the least cost?()
A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750.Which action allows the most efficient use of existing equipment?()
A customer would like to configure an uncapped LPAR so that it can use 2 to 8 cores depending on the workload characteristics. With SMT4 enabled, what is the least amount of processing resources which can be configured for the LPAR?()
Which of the following uses compression/decompression to increase the memory available for client workloads?()
A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()
Ancustomer with limited storage management skills needs a disk subsystem with up to 70TB capacity and enterprise class performance. Which disk storage system should be recommended?()
A customer requires two 12X loops on their new POWER7 system. What is the smallest system that will support two loops?()