單項(xiàng)選擇題

Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations. 
Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()

A.IBM eConfig
B.IBM Performance Monitor
C.IBM Workload Estimator (WLE)
D.IBM System Planning Tool (SPT)


您可能感興趣的試卷

你可能感興趣的試題

4.單項(xiàng)選擇題

A system is being designed with many LPARs which will be clients of dual VIO Servers. The VIO Servers must be redundant so that, in the event of scheduled maintenance, the clients do not need to be shut down. 
Which of these strategies could be used to ensure that the client LPARs continue to be able to use the network in the event of a VIO Server being shut down?()

A.Implement PowerHA SystemMirror on both VIO servers.
B.Configure Etherchannel between the client LPARs and the two VIO servers
C.Configure Network Interface Backup between the two VIO servers and use each VIO server to access the network.
D.Implement Shared Ethernet Adapter failover and have all client partitions access the network through the shared adapters.

5.單項(xiàng)選擇題

A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3).
Which of these statements is true and would minimize the cost?()

A.All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or later
B.The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMC
C.They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based  systems connected to the existing one
D.The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM

最新試題

A system is being designed with many LPARs which will be clients of dual VIO Servers. The VIO Servers must be redundant so that, in the event of scheduled maintenance, the clients do not need to be shut down.Which of these strategies could be used to ensure that the client LPARs continue to be able to use the network in the event of a VIO Server being shut down?()

題型:?jiǎn)雾?xiàng)選擇題

A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3).Which of these statements is true and would minimize the cost?()

題型:?jiǎn)雾?xiàng)選擇題

A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750.Which action allows the most efficient use of existing equipment?()

題型:?jiǎn)雾?xiàng)選擇題

A POWER7 processor has L1, L2 and L3 caches. Which of the three caches uses embedded DRAM (eDRAM) technology?()

題型:?jiǎn)雾?xiàng)選擇題

A customer is evaluating PowerVM and VMware to run a data warehouse application. Which feature of PowerVM should be highlighted as a differentiator?()

題型:?jiǎn)雾?xiàng)選擇題

Which of the following is a compelling reason to deploy IBM Systems Director Active Energy Manager (AEM) in a data center with high energy utilization?()

題型:?jiǎn)雾?xiàng)選擇題

A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()

題型:?jiǎn)雾?xiàng)選擇題

An end user is deploying Blade servers to replace obsolete rack mounted servers. In addition to AIX Web server and database workloads, they also have Windows workloads.Which Blade is designed for Windows workloads?()

題型:?jiǎn)雾?xiàng)選擇題

A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows.Which of the following design consideration statements is correct?()

題型:?jiǎn)雾?xiàng)選擇題

A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in thefollowing configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host1 hosted IBM i partition; 2 hosted Linux partitions.Which configuration will provide boot disk capability to all partitions?()

題型:?jiǎn)雾?xiàng)選擇題