A customer is planning on having a single Virtual I/O Server (VIOS) configuration in a Power 750. They haveselected a 4-port 1Gb Integrated Virtual Ethernet (IVE). There will be no other network cards installed in the system. One IVE logical port will be used in the VIO Server and will be used as the physicalport in a Shared Ethernet Adapter (SEA).
What is the maximum number of IVE logical ports available to use inother LPARs?()

A.1
B.7
C.15
D.31


您可能感興趣的試卷

你可能感興趣的試題

2.單項選擇題When considering migrating a POWER6 server with PCI-X and PCIe adapters to a Power 720, which statement is true?()

A.PCIe adapters are supported only in I/O drawers
B.PCI-X adapters are supported in both the CEC and in I/O drawers
C.PCI-X adapters are supported in the CEC; PCIe adapters are supported in 12X I/O drawers
D.PCIe adapters are supported in the CEC; PCI-X adapters are supported in 12X I/O drawers

5.單項選擇題

A customer has a 32-core Power 770 with 4 AIX partitions and 2 IBM i partitions. They want to improve network availability and allow for concurrent maintenance.
What will support the customer requirement at  least cost?()

A.Build the logical partition infrastructure based on 6 or more VLANs.
B.Build the logical partition infrastructure based on two or more IVEs.
C.Build the logical partition infrastructure based on Partition Mobility.
D.Build the logical partition infrastructure based on redundant VIO Servers.

最新試題

A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server.Which action will reduce the potential vendor software costs?()

題型:單項選擇題

A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows.Which of the following design consideration statements is correct?()

題型:單項選擇題

A customer has an LPAR with 4 dedicated cores on a POWER7 server with SMT4 enabled. How many logical processors are presented to an application running on this LPAR?()

題型:單項選擇題

A customer is evaluating PowerVM and VMware to run a data warehouse application. Which feature of PowerVM should be highlighted as a differentiator?()

題型:單項選擇題

Which system provides the highest performance per core, and the least cost for applications licensed per core?()

題型:單項選擇題

A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()

題型:單項選擇題

A customer would like to configure an uncapped LPAR so that it can use 2 to 8 cores depending on the workload characteristics. With SMT4 enabled, what is the least amount of processing resources which can be configured for the LPAR?()

題型:單項選擇題

A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3).Which of these statements is true and would minimize the cost?()

題型:單項選擇題

Which of the following is a compelling reason to deploy IBM Systems Director Active Energy Manager (AEM) in a data center with high energy utilization?()

題型:單項選擇題

A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750.Which action allows the most efficient use of existing equipment?()